Skip to content

Concrete Block Calculator

Enter wall length, height, and openings — get concrete/CMU/cinder block count, mortar bags, waste, and material cost.

Concrete blocks needed
149
14 bags mortar mix

Materials only. Excludes labour, forms, delivery, pump, finishing. Structural work requires local code compliance and engineer drawings.

Inputs
ft
ft
sf

Total sq ft — subtracted before block count

$
$/bag
10%
Diagramlive
Concrete block wall elevation20′6′
Wall area120 sf
Courses (rows)9
Blocks per course15
Mortar bags14
Results
Gross wall area120 sf
Net area (minus openings)120 sf
Blocks needed149
Mortar bags (est., 80 lb)14
Block cost$410
Mortar cost (est.)$182
Total cost (materials only)$592
How this is calculated

120 sf gross × 1.125 blocks/sf, then +waste = 149 blocks. Laid out as 9 courses of 15 blocks each (courses/blocks-per-course describe the wall's gross layout — they won't multiply back to the net block count when openings are entered).

Mortar is a rule-of-thumb estimate (~11 blocks per 80 lb bag, full face-shell bedding). Actual usage varies with joint thickness, block core size, and workmanship — buy 1-2 bags extra.

Edit price assumptions
$
$
$
$
$
$

How the concrete block calculator works

Standard concrete block (CMU — concrete masonry unit) has a nominal size of 8×8×16 inches, but the actual block measures 7.625×7.625×15.625 inches. The 3/8-inch gap on each dimension is the mortar joint, so a block plus its joint occupies a full 8×16-inch module of wall face. That module works out to 0.89 square feet, which means every square foot of wall needs about 1.125 blocks — the constant this calculator uses.

The calculation is simple multiplication: wall area (length × height, in square feet) times 1.125 gives the block count before waste. Add your waste allowance (10% default — covers cut blocks at corners and openings, plus breakage) and round up, since partial blocks can't be ordered. Mortar follows a similar rule of thumb: one 80 lb bag of mortar mix lays about 11 blocks with a full face-shell bed, so bags needed = block count ÷ 11.1, rounded up.

A worked example: a 20-foot wall, 6 feet tall. Wall area = 120 sq ft. Blocks before waste = 120 × 1.125 = 135. With 10% waste, that's 149 blocks. Mortar = 149 ÷ 11.1 = 14 bags. At $2.75 per block and $13 per bag of mortar, materials run 149 × $2.75 + 14 × $13 = $410 + $182 = $592 — before rebar, grout, footing, or labour.

The calculator also reports courses (rows) and blocks per course, which is useful for laying out the job before you order. Each course is 8 inches tall (one block height plus the mortar joint below it), and each block spans 16 inches of wall length. A 20-foot wall needs 20×12÷16 = 15 blocks per course; a 6-foot wall needs 6×12÷8 = 9 courses. Multiply those and you get 135 blocks for an opening-free wall — a useful way to sanity-check an order by hand. Note that courses × blocks-per-course describes the gross layout, so it won't match the block count once you enter door or window openings — those are subtracted from the area total, not from the course grid.

If the wall has doors, windows, or vents, enter their combined area in the Openings field before reading the block count — the calculator subtracts that area from the gross wall area first, so you're not buying and paying labour to lay blocks you'll immediately cut out for a frame.

Common block wall sizes and their material requirements (10% waste)
Wall size (l×h)Wall areaBlocks neededCoursesMortar bags
8′×4′32 sf4064
20′×6′120 sf149914
30′×6′180 sf224921
40′×8′320 sf3961236
50′×8′400 sf4951245
60′×8′480 sf5941254

Reinforcement — rebar, grout, and when you need an engineer

Unlike a poured concrete wall, a dry-stacked block wall gets its reinforcement inside the hollow cores of the blocks, not throughout the mass. Standard practice for a load-bearing or retaining CMU wall is vertical #4 or #5 rebar set in the cores at 32 to 48 inches on center, with those cores then filled solid with grout (a flowable, high-slump concrete mix designed to pour into narrow cavities without honeycombing).

Horizontal reinforcement matters just as much as vertical. Ladder-type or truss-type joint reinforcement — a welded wire ladder that sits in the mortar bed — is typically placed every 16 inches vertically (every other course) to control shrinkage cracking and tie the wall together horizontally. It's inexpensive (under $1 per linear foot) and is one of the most commonly skipped items on DIY block walls.

How much of this you actually need depends entirely on what the wall does. A short garden wall under 2 feet with no load on it can often get away with unreinforced block and mortar alone. A retaining wall holding back soil, a load-bearing wall carrying roof or floor framing, or any wall over 4 feet tall in a seismic or high-wind zone needs engineered reinforcement — and in most jurisdictions, a permit and inspection. This calculator estimates block and mortar only; it is not a substitute for an engineer's reinforcement schedule on structural walls.

If you do need grouted cells, budget separately for grout (roughly one 80 lb bag of grout fills 2–3 block cores 8 feet tall, depending on core size) and for the rebar itself — the rebar calculator on this site estimates linear feet and weight for a given spacing, which you can adapt to a vertical wall layout.

What the block wall estimate excludes

This calculator prices block and mortar only — the two materials every block wall needs regardless of design. Everything else depends on what the wall is for. A footing under the wall (the footing calculator on this site handles that separately), rebar and grout for structural cells, control joints (roughly every 20-25 feet to manage shrinkage cracking, using premolded joint filler), and cap block or a poured concrete cap on top of the wall are all common additions not included here.

Labour is the largest excluded cost. A skilled mason lays 80-120 blocks per day solo, or 150-200 with a helper mixing and delivering mortar. For a 149-block wall, that's roughly 1.5-2 days of skilled labour at $40-70 per hour — often more than the materials cost itself. This is one of the reasons block walls are frequently hired out even when concrete slabs are DIY'd: laying block plumb, level, and in a consistent running bond takes practice.

Other common exclusions: a gravel or compacted base under the footing, waterproofing or damp-proofing for below-grade walls, veneer or stucco finish over the block face, weep holes and drainage board for retaining walls, and equipment (mason's line, levels, a block saw for cuts at openings — $150-300 rental for a wet saw on a multi-day job). For a retaining wall specifically, add drainage gravel behind the wall and a perforated drain pipe at the base — skipping drainage is the single most common cause of retaining wall failure.

As with every calculator on this site, the number you get is a starting point for a materials order, not a full project budget. For a rough all-in estimate including labour, multiply the materials cost shown here by 2.5-3.5× for a simple garden wall, or budget separately with a mason's quote for anything structural or over 4 feet tall.

FAQ

Built and maintained by Rizwan. Calculations are performed client-side using published manufacturer bag yields, ACI mix ratios, and ASTM rebar specifications. Every formula and worked example on this site can be verified by hand against the sources listed below.

Sources: Quikrete technical data sheets; ACI 318 Building Code Requirements for Structural Concrete; ASTM A615 rebar specifications; US Concrete Institute material weights.

Last reviewed: August 2026. Prices reviewed quarterly. Affiliate disclosure: this page may contain Amazon affiliate links. See privacy policy.

CMU / FIELD GUIDE

How many concrete blocks do I need?

CountMaterials uses the wall dimensions, subtracts any door or window openings, and applies the standard 8 × 16 inch CMU face module. That gives a practical block quantity before waste, then the calculator rounds up and adds your selected waste allowance. The default estimate is designed for ordinary U.S. concrete masonry work and is intended for material planning, not structural design.

01 / FORMULA

Block count formula

Gross area = length × height
Net area = gross area − openings
Base blocks = net area × 1.125
Final blocks = round up(base × (1 + waste))

The 1.125 factor comes from a nominal 8 × 16 inch block face including a typical 3/8 inch mortar joint. Actual quantities vary with block geometry, joint thickness, bond pattern, cuts and site conditions.

02 / EXAMPLE

20 × 8 ft block wall

Gross wall160 sf
Openings0 sf
Base blocks180
10% waste18
Order quantity198 blocks

If the same wall has 20 sf of doors and windows, the net area becomes 140 sf and the block estimate drops accordingly. Enter the total opening area in the calculator rather than estimating it separately.

Common CMU sizes
Nominal blockBlocks / sf*Typical wall thickness
4 × 8 × 16 in~1.1254 in wall
6 × 8 × 16 in~1.1256 in wall
8 × 8 × 16 in~1.1258 in wall
10 × 8 × 16 in~1.12510 in wall
12 × 8 × 16 in~1.12512 in wall

*Approximate face-module planning rate. Wall thickness changes material volume, weight and mortar/core requirements; it does not change the nominal face count when the block face is 8 × 16 inches.

03 / OPENINGS

Doors & windows

Subtract opening area before multiplying by the block rate. For multiple openings, add their individual width × height areas together.

04 / MORTAR

Mortar estimate

Mortar is shown as an estimate based on standard face-shell bedding. Joint thickness, block type, workmanship and waste can change actual bag usage.

05 / WASTE

Plan for cuts

Corners, bond patterns, damaged units and field cuts create waste. Use a lower allowance only when the wall layout is well controlled.